Trenches have been dug for the footings – the ground was so hard it broke one of the teeth on the bucket of the trench digger!
The hole for the septic tank has been dug outside the Western Room.
Plumbing for kitchen and toilets have been created and the conduits which will carry audio/lighting and projection cables have been laid under the future foundation.
Kynan Brookes
Slab Poured - click to see photo
Our building development is running on schedule! This week the slab was poured in two parts. The first slab was the area outside the front offices and the Northern entrance, kitchen and toilets. The second slab poured will be the auditorium. It has been poured to create two slabs so that sound vibrations will not travel from the auditorium to the offices and new welcome centre.
Building will halt for a short time over the Christmas break
Major Redevelopment Underway
Friends you will notice that siteworks are beginning at 1263 Grand Junction Road. This is an exciting and challenging time for us. The current facilities are still in use - except for the shed! When you arrive for worship please be aware that carparking will be different from week to week. We encourage you to leave a little earlier and park off site if possible.